Which sequence correctly adds a Completed Status to a markup?

Prepare for the Bluebeam University Exam. Utilize flashcards, multiple-choice questions, and explanations to ensure success. Get exam-ready!

Multiple Choice

Which sequence correctly adds a Completed Status to a markup?

Explanation:
The key idea is how to update a markup’s lifecycle by using the Markup List and the Status control. To mark a markup as Completed, you must first select that specific markup in the Markup List, then open the Status option and choose Completed under the Review category. This updates the item’s state in the workflow and reflects the completion across the document. Using the Color icon changes how the mark appears but not its status. The Tool Chest is for applying tools and markups, not updating their status. Exporting the markup to PDF doesn’t alter its status either. If you don’t have the markup selected, applying a status has nothing to apply to.

The key idea is how to update a markup’s lifecycle by using the Markup List and the Status control. To mark a markup as Completed, you must first select that specific markup in the Markup List, then open the Status option and choose Completed under the Review category. This updates the item’s state in the workflow and reflects the completion across the document.

Using the Color icon changes how the mark appears but not its status. The Tool Chest is for applying tools and markups, not updating their status. Exporting the markup to PDF doesn’t alter its status either. If you don’t have the markup selected, applying a status has nothing to apply to.